Following their appointment to complete the construction works at Wilson Sports Village, Universal Civils & Build have been advancing the project since January. Their efforts have not only focused on construction but also on building strong community links.

Outside view of building on construction site featuring glazing

March Progress:

  • External Brickwork and Cladding: Significant progress has been made on the external brickwork and cladding, enhancing the structural integrity and aesthetic appeal of the facility.
  • Fit-out of the Plant Room: The plant room has been fitted out, ensuring that essential mechanical and electrical systems are in place.
  • Internal Walls and Steel Painting: Internal walls have been constructed and painted, and steel structures have received a protective coat of paint.
  • Pool Slabs and Preparation for Tiling: The pool slabs have been laid, and preparations for tiling are underway.

Upcoming Work in April and May:

  • Internal Screeding, Plastering, and Tiling: Internal screeding, plastering, and tiling will commence, contributing to the interior finish of the facility.
  • Completion of Brickwork: The remaining brickwork will be completed, finalising the external structure.
  • Installation of Solar Panels: Solar panels will be installed, supporting the project’s commitment to sustainability and renewable energy.